Multiple choice

Which of the following is used to refine the initial requirements, refine the architecture, monitor the risks, refine their properties and produce the project management plan?

  1. Construction phase

  2. Inception phase

  3. Elaboration phase

  4. Software verification review

  5. Both 1 and 2

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Its aim is to refine the initial requirements, refine the architecture, monitor the risks, refine their priorities and produce the project management plan.