Multiple choice

Directions: Refer to the following information and the answer the following question. People Power Corporation presently employs three Managers (A, B and C) and five recruitment agents (D, E, F, G and H). The company is planning to open a new office in San Jose to manage placement of software professionals in the US. It is planning to relocate two of the three managers and three of the five recruitment agents to the office at San Jose. As it is an organization which is highly people oriented the management wants to ensure that the individuals who do not function well together should not be made as a part of the team going to the US. The following information was available to the HR department of People Power Corporation. Managers A and C are at each others throat and therefore cannot be sent as a team to the new office. C and E are excellent performers in their own right. However, they do not function together as a team. They should be separated. D and G have had a major misunderstanding during the last office picnic. After the picnic these two have not been in speaking terms and should therefore not be sent as a team. D and F are competing for a promotion which is due in another 3 months. They should not be a team.

If A is to be moved as one of the Managers, which of the following cannot be a possible working unit?

  1. ABDEH

  2. ABFGH

  3. ABEGH

  4. ABDGH

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

D and G cannot be part of the same team. Answer:  (4)