If x and y can do a piece of work in 12 day, y and z can do the same work in 15 days, and x and z can do that work in 20 days, then find the number of days required to finish the work if all (x y z) work simultaneously and the work starts with z.

  1. 12 days

  2. 51/2 hours

  3. 51/2 days

  4. 5 days

  5. 25 days

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Correct