Multiple choice

Directions: Choose the correct option for the given question: The principal budget factor constitutes the starting point for the preparation of various budgets.

  1. True

  2. False

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

The principal budget factor (or limiting factor) is the factor that restricts the volume of activity, and it must be identified first to ensure the budget is realistic.