Multiple choice

The two levels of material control are quantity control and

  1. financial control

  2. value control

  3. quality control

  4. both (2) and (3)

  5. all of the above

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Material control is generally divided into quantity control (ensuring the right amount is available) and financial/value control (ensuring the cost of materials is monitored and optimized).