Multiple choice

When job is very big and spread over long periods of time, the method of costing adopted is

  1. process

  2. job

  3. contract

  4. operation

  5. batch

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Contract costing is specifically designed for large projects that span long periods, such as construction or civil engineering projects.