_____ is a predetermined cost.

  1. Marginal cost

  2. Standard cost

  3. Service cost

  4. Unit cost

  5. Historic cost

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

A standard cost is a predetermined cost that is calculated based on management's standards of efficient operation and the relevant necessary expenditure.

Keep practicing — related questions

  • Directions: Choose the correct option for the given question. Standard cost is a/an
  • Directions: Choose the correct option for the given question. _____ costing cannot be used in small concerns.
  • Directions: Choose the correct option for the given question. ______ is based on the distinction between fi...
  • Directions: Choose the correct option for the given question. _____ expenses are excluded from cost.
  • Directions: Choose the correct option for the given question. _____ costing is widely used in engineering i...
  • Directions: Choose the correct option for the given question. There will be _____ in marginal costing, when...
  • Directions: Choose the correct option for the given question. Profit planning is possible with _____ costing.
  • Directions: Choose the correct option and complete the sentence. The cost which can be conveniently identif...
Play the full quiz 🎤 Practise this topic out loud
Advertisement
© Aliensbrain | all rights reserved
  • About
  • Contact
  • Terms and Condition
  • Privacy Policy