Multiple choice

A software organisation has been assessed at SEI CMM Level 4. Which of the following does the organisation need to practice besides process change management and technology change management in order to achieve Level 5?

  1. Defect detection

  2. Defect prevention

  3. Defect isolation

  4. Defect propagation

  5. None of these

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

It is required to be practiced to achieve CMM Level 5.