Multiple choice

How many districts have been identified in the first phase of National Rural Employment Guarantee Programme 2005?

  1. 150

  2. 200

  3. 250

  4. 300

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

The National Rural Employment Guarantee Act (NREGA) was implemented in 2005-06 with 200 districts in its first phase. The scheme was subsequently expanded to all districts in later phases. The numbers 150, 250, and 300 are incorrect for the initial phase.