In spiral model, which of the following phases has the task to build one or more representations of the applications?

  1. Engineering

  2. Planning

  3. Risk analysis

  4. Construction and release

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Engineering phase task is required to build one or more representations of the applications.

Keep practicing — related questions

  • _______ phase in the spiral model is used to define resources, timelines and other project related informat...
  • Which of the following phases in spiral model obtains customer feedback based on evaluation of the software...
  • Which of the following can be represented schematically as a series of major technical activities, tasks an...
  • Which is the process of determining the input values required to achieve a certain mission?
  • Which of the following takes into account input variables, interrelationships among the variables, problem ...
  • The spiral model of software development
  • Which model accommodates life cycle evolution, growth and requirement changes?
  • Which of the following models incorporates prototyping as a risk reduction strategy?
Play the full quiz 🎤 Practise this topic out loud

Practice this topic

  • Software Development and Management (3064 questions)
Advertisement
© Aliensbrain | all rights reserved
  • About
  • Contact
  • Terms and Condition
  • Privacy Policy