Which among the following is not the responsibility of Central Electricity Regulatory Commission that was established in 1998?

  1. To improve the operations and management of the regional transmission systems through Indian Electricity Grid Code (IEGC) and Availability Based Tariff (ABT).

  2. To facilitate open access in interstate transmission.

  3. To dissolve the disputes between power generation and distribution authorities.

  4. Facilitate technological and institutional changes required for the development of competitive markets in bulk power and transmission services.

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

CERC handles IEGC (Indian Electricity Grid Code), ABT (Availability Based Tariff), and facilitates open access and competitive markets in power transmission. However, dispute resolution between generation and distribution authorities is handled by Electricity Regulatory Commissions and Appellate Tribunals, not CERC directly. CERC focuses on tariff regulation and grid operations, not dispute dissolution.