You are the supervisor of a construction site. Which of the following teams would you stop from doing work during a thunderstorm? (a) The plumbing team laying the galvanised iron pipes (b) The carpenter team hammering nail into a wooden structure lying on the ground floor (c) The mason and labour team constructing an inside partition wall (d) The scaffolding team installing the metallic scaffolding on the outside walls
Reveal answer
Fill a bubble to check yourself