Multiple choice

Which of the following approaches in Software Development Life Cycle is more flexible and assumes that the project cannot be planned out completely in advance but must be modified as it progresses?

  1. Predictive approach

  2. Project planning

  3. Adaptive approach

  4. Analysis

  5. Project

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

This approach in Software Development Life Cycle is more flexible and assumes that the project cannot be planned out completely in advance but must be modified as it progresses.