Multiple choice

What is the time required for the scheduler to stop one process and start another process called?

  1. Response time

  2. Waiting time

  3. Turnaround time

  4. Throughput

  5. Dispatch latency

Reveal answer Fill a bubble to check yourself
E Correct answer
Explanation

Dispatch latency is the amount of time required for the scheduler to stop one process and start another.