Multiple choice

In which of the following phases of system development life cycle is the total cost of generating the software estimated together with the total period of the project?

  1. System analysis

  2. Feasibility study

  3. System planning

  4. System design

  5. System testing

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

This phase of system development life cycle the total cost of generating the software is estimated together with the total period of the project.