Multiple choice

Why is it necessary to perform feasibility study before developing a system?

  1. It lets the developer analyse the proper resources required to develop the system.

  2. It lets the developer estimate the proper time or deadline for the system.

  3. It lets the developer check the economic status of the system.

  4. All of the above

  5. Feasibility study bears no relationship with project development.

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Feasibility study is of various types such as technical, economical, operational, legal, etc. and all are required if you wish to complete the project successfully.