In a SCRUM project, the productivity of the team is termed as
-
Velocity
-
Burned down
-
SPRINTS
-
None of the above
A
Correct answer
Explanation
In SCRUM, velocity is the metric that measures a team's productivity - specifically, the amount of work (usually in story points or hours) the team completes per sprint. A burn-down chart tracks remaining work over time, sprints are time-boxes, and velocity is used for predictable planning.