Multiple choice technology architecture

The requirements selected from the product backlog into Sprint back log can not be changed in the middle of the SPRINT

  1. True

  2. False

  3. None

  4. Don't Know

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Once requirements are moved from the product backlog to the sprint backlog, they should not be changed during the sprint. This protects the team from scope creep and allows them to commit to a realistic goal. Changes must wait for the next sprint planning session, though the team can voluntarily adjust scope if they finish early.