Passage
Directions : Study the following information and answer the question. A company has assigned grades to its workers according to their capability, i.e. grades A, B and C. The total number of workers in the company is 120. I. The grade A workers can complete the project alone in 120 hours. The ratio of the number of grade A workers to that of grade B workers is 3 : 5. II. The grade B workers are half as efficient as the grade A workers. The number of grade B workers is 16 less than that of grade C workers. III. The grade C workers are half as efficient as the grade B workers. The total number of workers of grades B and C is 96.
On what day of the week will the project be finished if all the workers work together, given that the working days are from Monday to Friday and there are 8 working hours in a day? It is also given that the project starts on Friday.