Passage
Directions: The data below represents the number of people required for various project to be completed in different number of days. Use this information to answer the question asked. Project Situation I Situation II Number of Workers Number of Days Required Number of Workers Number of Days Required P 1 x (x + 5) (x – 5) (x + 15) P 2 y (y + 10) 40 (y – 5) P 3 50 z 80 (y – 10) P 4 y (z – 1) (x + 10) (z – 4)
In a group A, if the total number of workers is (0.2x × 0.8y), then what is the number of days required by group A to complete Project P2, given y > 15?
Reveal answer
Fill a bubble to check yourself