Multiple choice

Ajay and Babar were scheduled to start a project at 9:00 AM in the morning, but one of them joined the work one hour after schedule, i.e., at 10:00 AM, while the other was on schedule. If it is given that, the project would be completed at 3:00 PM on the same day had Babar been late and at 2:30 PM on the same day had Ajay been late, then find the scheduled time when the project was supposed to be completed.

  1. 2:00 PM

  2. 2:15 PM

  3. 1:00 PM

  4. 1:45 PM

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Let T be the scheduled time. Let A and B be the rates of Ajay and Babar. The total work W = (A+B)(T-9). If B is late, (A+B)(15-9) = A*(15-9) + B*(15-10) is not quite right; solving the system of equations leads to 2:15 PM.

AI explanation

Let A and B be the efficiencies of Ajay and Babar, and let T be the scheduled completion time in hours from 9 AM. The first condition gives the equation A multiplied by T plus B multiplied by (T minus 1) equals the total work. The second condition gives the equation A multiplied by (T minus 1) plus B multiplied by T equals the total work. Setting these two equations equal to each other results in AT plus BT minus B equaling AT plus BT minus A, which simplifies to A equals B. Since their efficiencies are equal, the scheduled time must be exactly halfway between the two actual completion times of 5.5 hours and 5 hours. Averaging 5.5 and 5 gives a scheduled time of 5.25 hours from 9 AM. This time of 5 hours and 15 minutes corresponds to 2:15 PM. The correct answer is 2:15 PM.