If A and B can do a piece of work in 6 days, B and C in 8 days and C and A in 12 days, then A alone can do the work in how many days?
Reveal answer
Fill a bubble to check yourself
If A and B can do a piece of work in 6 days, B and C in 8 days and C and A in 12 days, then A alone can do the work in how many days?
16 days
24 days
18 days
152/3 days
Cannot be determined
Let rates be A+B=1/6, B+C=1/8, C+A=1/12. Adding these: 2(A+B+C) = 1/6 + 1/8 + 1/12 = (4+3+2)/24 = 9/24 = 3/8. So A+B+C = 3/16. A = (A+B+C) - (B+C) = 3/16 - 1/8 = 3/16 - 2/16 = 1/16. Thus, A takes 16 days.
Using the LCM method, let the total work be the least common multiple of 6, 8, and 12, which is 48 units. The combined rates of (A+B), (B+C), and (C+A) are 8, 6, and 4 units per day respectively. Adding these gives 2(A+B+C) = 18 units per day, so the combined rate of A+B+C is 9 units per day. A's rate is the total rate minus B+C's rate: 9 - 6 = 3 units per day. Therefore, A alone can complete the 48 units of work in 48 / 3 = 16 days.