20 men can do a piece of work in 24 days and 30 women can do the same work in 36 days. 12 men started working on first day and 24 women working on second day, then find the no. of days required to complete the whole work

  1. 42 1/3

  2. 21 1/3

  3. 27 2/3

  4. 39 1/3

  5. 41 2/3

Reveal answer Fill a bubble to check yourself
A Correct answer

Keep practicing — related questions

  • Out of three numbers, the first is 16 times the second and 4 times the third. If the average of all the thr...
  • Mohan works at a bakery. He must box 30 cakes, 24 pastries, and 48 biscuits so that all of the boxes have t...
  • Find the least number which when divided by 36, 16, 24 and 48 leaves the remainder 7 in each case.
  • Directions: A sentence is given in four parts (P, Q, R, and S). One of the parts contains a grammatical err...
  • Which of the following is the total amount required to buy 200, Rs. 75 shares at a premium of 12%?
  • An infant passes greenish faecal matter in first two days of birth. This is known as
  • Stock is appearing in the books at Rs. 36,000 and it is undervalued by 20%. How to treat it in the revaluat...
  • Why do chalk pieces first float on water, but after sometime sink?

Practice this chapter

  • Time and Work (2195 questions)
Advertisement
© Aliensbrain | all rights reserved
  • About
  • Contact
  • Terms and Condition
  • Privacy Policy