30 men working together can build the concrete pavement for an entire city in 270 days. Due to unforeseen circumstances the work had to be stopped 30 days before it was over, and the contractor was given a time limit of 12 days to complete the rest of the work. How many more workers would the contractor have to employ to get the work done on time?