4 women and 5 men can complete a certain work in X days, while 4 men and 1 woman can complete the same work in Y days. The work completed by 1 man in 1 day is 250% of the work completed by 1 woman in 1 day. Which of the following is the ratio of the number of days required to complete the work by 4 women and 5 men together and the number of days required to complete the work by 4 men and 1 woman together? (i) 5 : 3 (ii) 2 : 3 (iii) 4 : 3 (iv) 6 : 5