Multiple choice

Sajan is able to do a work in 35 days. Calculate the number of days taken by Tanvir to do the same work, if she is 40% more efficient.

  1. 10 days

  2. 15 days

  3. 25 days

  4. 29 days

  5. Na

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

If Tanvir is 40% more efficient than Sajan, her efficiency ratio is 1.4 times Sajan's. Since time taken is inversely proportional to efficiency, Tanvir takes 35 / 1.4 = 25 days.