A contractor estimates that $3$ persons could rewire Jasminders house in $4$ days. If he uses $4$ persons instead of three, how long should they take to complete the job?
Reveal answer
Fill a bubble to check yourself
A contractor estimates that $3$ persons could rewire Jasminders house in $4$ days. If he uses $4$ persons instead of three, how long should they take to complete the job?