Which three are true about using breakpoints to suspend processes in the TIBCO Designer Tester Utility?(Choose 3)

  1. can be conditional

  2. persist after you close a project

  3. cannot be set after the End activity

  4. cannot be set on all activities in a process

Reveal answer Fill a bubble to check yourself
A,B,C Correct answer
Explanation

Breakpoints can be conditional based on process variables or data, they persist across project sessions, and cannot be placed after the End activity since there is no execution after it. Breakpoints can be set on virtually all activities in a process, not just a limited subset.