A and B can do a piece of work in 10 days and 15 days. They started the work for Rs. 2625, and complete it in 4 days with help of C. Find the share of C.
Reveal answer
Fill a bubble to check yourself
A and B can do a piece of work in 10 days and 15 days. They started the work for Rs. 2625, and complete it in 4 days with help of C. Find the share of C.