A can do a piece of work in 15 days and B in 20 days. How much time will they take to complete the work if they work on alternate days, starting with A?

  1. 13 days

  2. 15 days

  3. 17 days

  4. 19 days

  5. 23 days

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

A's work rate is 1/15 per day, B's work rate is 1/20 per day. Working alternately starting with A, in 2 days they complete 1/15 + 1/20 = 4/60 + 3/60 = 7/60 of the work. After 16 days (8 cycles of 2 days), they complete 8 × 7/60 = 56/60, leaving 4/60. On day 17, A works and completes 1/15 = 4/60, finishing the job. Total time = 17 days.