Multiple choice

A began to do a job alone. After 6 days, he was joined by B. They both worked for another 5 days, after which they were joined by C. Three of them completed the work in a further period of 9 days. How long would C take to do the entire work alone, assuming that A and B separately could do the whole work in 36 days and 42 days, respectively?

  1. 90 days

  2. 81 days

  3. 72 days

  4. 60 days

Reveal answer Fill a bubble to check yourself
B Correct answer
AI explanation

Assuming the total work is the least common multiple of 36 and 42, which is 252 units, A's daily work is 7 units and B's is 6 units. A works for a total of 20 days (6 plus 5 plus 9), completing 140 units. B works for a total of 14 days (5 plus 9), completing 84 units. The work done by A and B is 224 units, leaving 28 units for C, who worked for 9 days. C's daily work is 28 divided by 9, so C alone would take 252 divided by (28/9) days. C takes 81 days to do the entire work alone.