Multiple choice

6 boys or 4 men can complete a piece of work in 24 days. In how many days will 3 boys and 10 men together complete the same piece of work?

  1. 6 days

  2. 8 days

  3. 12 days

  4. Cannot be determined

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

6 boys = 4 men, so 1 boy = 2/3 man. The work is done by 3 boys + 10 men = 3(2/3) + 10 = 12 men. Since 4 men take 24 days, 12 men take (4*24)/12 = 8 days.