Directions: Study the given information carefully and answer the question that follows. Sachin takes up a project to be completed in 20 days. It requires 5 men to work continuously through all the days. Before commencement of the project, Mr. Virat, Sachin's client, informs him that he wants the project to be completed ahead of the given time. So, Sachin figures he will have to increase 5 men every 2 days to meet Mr. Virat's condition. On the day of completion of project (the day specified by Mr. Virat), how many men would be working?