Multiple choice

If 2 men can complete a task in 8 days, how many men are required to complete the same task in 4 days?

  1. 3

  2. 4

  3. 5

  4. 6

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Using M1 * D1 = M2 * D2, 2 * 8 = M2 * 4. 16 = 4 * M2, so M2 = 4.

AI explanation

Using the formula M1D1 = M2D2, we substitute the given values to get 2 men multiplied by 8 days equals the required men multiplied by 4 days. This simplifies to 16 = 4 multiplied by the required men. Dividing both sides by 4 gives the required number of men as 4.