Multiple choice

A work can be done by 5 men in 12 days. How many more men are required to do double the work in half time?

  1. 17

  2. 15

  3. 10

  4. 12

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Work formula: (M1 * D1) / W1 = (M2 * D2) / W2. (5 * 12) / 1 = (M2 * 6) / 2. 60 = 3 * M2, so M2 = 20. Total men needed is 20. Since 5 are already there, 15 more are required.

AI explanation