It takes 4 workers working at equal rates to finish a job in 48 days. How long will 3 workers take to finish the same job?

  1. 64 days

  2. 36 days

  3. 48 days

  4. None of these

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Work = Workers * Days. 4 * 48 = 3 * D. D = (4 * 48) / 3 = 4 * 16 = 64.

AI explanation

By the inverse proportionality method between workers and days, the product of workers and days remains constant. We set up the equation 4 workers multiplied by 48 days equals 3 workers multiplied by the unknown number of days. Solving this gives 192 equals 3 times the days, so the days equal 64. It will take 3 workers 64 days to finish the job.