Multiple choice technology platforms and products

Work Parties are interested in the progress and resolution of a particular work object, but do not perform work in the application.

  1. True

  2. False

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Work Parties in Pega are stakeholders who have an interest in a work object's progress and outcome (like a customer, manager, or external party) but they don't perform the actual work within the application. They're kept informed of status changes and resolutions.