Multiple choice technology mainframe

The GDG is created in the first step and it is used in the second step. What are all changes we should do if the job abended in the 2nd step?

  1. Restart parameter should be used

  2. Have to start from the 1st step again to get the GDG to be created again

  3. The GDG version should be changed from (+1) to (0)

  4. None of the above

Reveal answer Fill a bubble to check yourself
A,C Correct answer
Explanation

When a job fails in the second step after creating a GDG in the first step, you restart from the failed step using the RESTART parameter. Since the generation was already created in step one, it must now be referenced as (0) rather than (+1) during the restart run.