B has a requirement of A with lead time of 2 hours. B was triggered at 8:00 AM and is active. What should be the minimum time at which A might have completed.

  1. 6:00 AM

  2. 5:59 AM

  3. 6:01 AM

  4. Could be any time as the run time of A is not specified. Question needed additional information.


Correct Option: D

Find more quizzes: