Multiple choice technology mainframe

The job where it has positive dependency on may not be necessarily be the job that triggers it. State whether this staement is true or false

  1. True

  2. False

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Positive dependency means Job B requires Job A to complete before B can run. However, Job A completing does NOT necessarily trigger Job B - B might need other conditions satisfied first, or B might be triggered by a different job entirely. Dependency is about prerequisites, not triggers.