Which one is not a sub process mapping technique
-
Process Flow Chart
-
Critical Path Method
-
Alternate Path Method
-
Deployment Flow Chart
B
Correct answer
Explanation
Process Flow Chart, Deployment Flow Chart, and Alternate Path Method are all techniques used for mapping and analyzing processes at various levels. Critical Path Method (CPM) is a project management technique used for scheduling and determining task dependencies in projects, not a process mapping technique. CPM deals with time and resource allocation in projects, not process workflow mapping.