Multiple choice six-sigma green-belt

Which one is not a sub process mapping technique

  1. Process Flow Chart

  2. Critical Path Method

  3. Alternate Path Method

  4. Deployment Flow Chart

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Process Flow Chart, Deployment Flow Chart, and Alternate Path Method are all techniques used for mapping and analyzing processes at various levels. Critical Path Method (CPM) is a project management technique used for scheduling and determining task dependencies in projects, not a process mapping technique. CPM deals with time and resource allocation in projects, not process workflow mapping.