What is correct sequence in SmartBuild

  1. Class Structure, Properties, User Interface, Activities

  2. Class Structure, Properties, Activities,User Interface

  3. Properties, Class Structure, User Interface, Activities

  4. Class Structure, Activities,Properties, User Interface

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

SmartBuild in PRPC follows a specific development sequence: Class Structure first (define data model), then Properties (define attributes), then User Interface (build screens), and finally Activities (add automation). This sequence ensures data exists before UI references it, and UI exists before business logic manipulates it.