Which of the following is not one of the four parts of a fully developed CTQ
-
Output Characteristic
-
Project Y Metric
-
Deadline
-
Target
C
Correct answer
Explanation
A fully developed Critical to Quality (CTQ) tree typically includes the Customer Need, the Driver, and the CTQ Requirement (which includes a Metric and a Target). While a deadline is important for project management, it is not one of the four standard technical components of a CTQ characteristic.