Multiple choice six-sigma green-belt

Which of the following is not one of the four parts of a fully developed CTQ

  1. Output Characteristic

  2. Project Y Metric

  3. Deadline

  4. Target

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

A fully developed Critical to Quality (CTQ) tree typically includes the Customer Need, the Driver, and the CTQ Requirement (which includes a Metric and a Target). While a deadline is important for project management, it is not one of the four standard technical components of a CTQ characteristic.