Multiple choice technology platforms and products

Router, Notify and Utility SmartShapes reference which rule type?

  1. Flow Action

  2. Activity

  3. Flow

  4. Model

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

In Pega, Router, Notify, and Utility shapes in a flow diagram reference Activity rules to perform their respective backend processing, routing, and notification tasks.