The Neyveli thermal power plant is fed by
-
Gondwana coal
-
Tertiary coal
-
Cambrian coal
-
Quaternary coal
B
Correct answer
Explanation
Neyveli in Tamil Nadu is famous for its lignite deposits, which belong to the Tertiary geological period (approximately 2-66 million years ago). The Neyveli thermal power station is specifically designed to burn this lignite. Gondwana coal is much older (Permian period), while Cambrian and Quaternary are not relevant coal classifications in India.